Harbor Bay Community Development District Seawall Announcement

Harbor Bay Community Development District Seawall Announcement

On July 11, 2019, the Harbor Bay Community Development District (District) signed an agreement with the Florida Structural Group, Inc. (FSG) to complete the seawall repairs throughout the entire community (approximately 32,000 linear feet) at the price of $17,449,213.

For details regarding the planned bond financing and refinancing of the project, please refer to the July 18 Agenda. Repairs should begin in mid to late October 2019, once bond financing has been obtained, final designs have been approved, and FSG has mobilized to the site.

Substantial completion of the entire project is anticipated in 2Q 2021.